Sulfite recovery boiler (SulfitePower), at Sappi Saiccor, South Africa

ANDRITZ to supply complete drying and incineration system for one of the world’s largest wastewater treatment plants in Bailonggang, Shanghai

2018/05/22

International technology Group ANDRITZ has received an order to supply a complete drying and incineration system for the expansion of the Bailonggang wastewater treatment plant in Shanghai.

The order value for ANDRITZ is almost 120 million euros. Construction work will start at the end of 2018, with first firing expected by the end of 2019.

The technology supplied by ANDRITZ includes sludge handling, nine fluidized bed dryers, six EcoFluid bubbling fluidized bed boiler lines including the entire flue gas cleaning, as well as full plant automation. The scope of supply further comprises engineering, manufacturing, delivery, and supervision of both installation and commissioning.

Located in the city of Shanghai and close to Pudong International Airport, the Bailonggang wastewater treatment plant is one of the world’s largest effluent treatment plants and the largest in Asia. Upon completion, the expansion project will have an installed capacity of up to 3,000 tons sludge per day. The plant is set to be the world's largest sludge incineration plant and will serve as a landmark among Chinese environmental projects.